How long does a solar permit take to get approved?

Plan review for a rooftop solar permit often takes about a week, or no time at all through SolarAPP+. Final inspection and utility approval take longer.

Every homeowner asks how long the permit will take, usually right after signing and right before telling their neighbors the panels go up next week. The honest answer has two parts: the permit itself is often the quick part, and the calendar is mostly eaten by everything around it.

How long does a solar permit take to get approved?

For a typical residential rooftop system, plan review takes about a week in many jurisdictions, and no time at all where the city uses SolarAPP+. In NREL's review of 2022 data, the median permit review for PV-only projects was 7 business days through traditional local review and 0 days through SolarAPP+, which approves code-compliant applications instantly.

That is the review. The full permit, from submission to a passed final inspection, runs much longer: a median of 51 business days for traditionally permitted PV-only projects in the same data, and 38 for SolarAPP+ projects. Most of the difference between "approved" and "finished" happens after the permit is issued.

The rest of this post breaks that timeline into its pieces, so you can see where the days actually go.

The five stages of a solar permit timeline

A residential solar job moves through five stages before the customer can turn the system on:

  1. Intake. The jurisdiction checks that the application is complete before anyone reviews it.
  2. Plan review. A reviewer checks the electrical design, the structural attachment and the roof layout.
  3. Corrections. If the reviewer has comments, the plans go back, get revised and come back in.
  4. Inspection. After installation, the inspector checks the work in the field. Some jurisdictions require more than one visit.
  5. Permission to operate (PTO). The utility installs or reprograms the meter and gives the go-ahead to energize.

Stages 1 through 3 are the "approval" most people mean when they ask the question. Stages 4 and 5 are why the customer is still asking in month two.

Intake: the first few days

Intake sounds like paperwork for the paperwork, and it is. It still matters, because an application that is not accepted as complete has not started its review clock.

Florida puts a number on this step. Under section 553.792 of the Florida Statutes, a local government has 5 business days after receiving an application to tell the applicant in writing what is missing. If it does not send that notice in time, the application is treated as complete and accepted.

Most states do not set a deadline for intake, which means an incomplete application can sit quietly until someone notices.

Plan review: where state deadlines apply

Several states set a deadline for the building department to act on a permit application. A few that matter for residential solar work:

  • Massachusetts: the building official must issue or deny the permit in writing within 30 days of filing (780 CMR 105.3.1). Missing that deadline does not approve the permit; it gives the applicant grounds for a complaint or an appeal.
  • New Jersey: the construction official must approve or deny an application within 20 business days (N.J.A.C. 5:23-2.16).
  • Florida: residential permits for structures under 7,500 square feet have a 30-business-day deadline. Single-trade permits, including electrical, on an existing single-family home have a 5-business-day deadline, but only where the value of the work is under $15,000, which many solar systems are not. A local government that misses its deadline has to cut the permit fee by 10 percent for each business day it is late, unless the delay is the applicant's or an exception applies.

These are ceilings, not typical times. Plenty of cities do much better. Lowell, Massachusetts, for example, says it issues most permits within three days of receiving a completed application.

The word doing the work in all of these rules is "complete." A deadline only protects you if the application is complete when it goes in.

SolarAPP+: the fastest review there is

SolarAPP+ is an automated permitting platform built by NREL. Where a jurisdiction participates and the system qualifies, the application is checked against code automatically and the permit can be issued the same day.

NREL's 2023 data shows what that does to the whole timeline. The median time from permit submission to a passed final inspection for PV-only projects was 33 days through SolarAPP+ and 47.5 days through traditional permitting, about 31 percent faster. By the end of 2023, 97 local governments had publicly launched the platform.

Two things to keep in mind. SolarAPP+ replaces plan review, not inspection, so the system still has to pass in the field. And it does not speed up every job equally: in NREL's 2022 data, solar-plus-storage projects through SolarAPP+ took longer from submission to final than traditionally permitted ones, which NREL attributed mostly to factors outside the platform, such as the time from issuance to first inspection.

Corrections: the stage you control

Each round of corrections adds a full trip through the review queue. The reviewer writes comments, the designer revises, and the application goes back into the queue.

Florida is one of the few states that sets a deadline here too: once revisions come in, the local government has 10 business days to act on them.

Most first-pass corrections on solar come from a short list: busbar math that does not support the breaker as drawn, fire access pathways drawn to the model code instead of the local amendment, missing or out-of-state structural stamps, and applications whose scope does not match the plan set. Our post on what permits you need to install solar panels covers each of those requirements in more detail. Catching them before filing is the cheapest time saving available in the whole process.

Inspection: usually the longest wait after approval

Once the permit is issued, the job has to be scheduled, installed and inspected. A typical residential installation takes one to two days, according to Eversource, though crew backlogs and parts can push the start date out.

The inspection is where calendars drift. Some jurisdictions require a single final. Others require a rough inspection before the panels go on and a final after. Each one needs an open slot on the inspector's schedule, someone to provide access, and in some places a license holder on site. A failed inspection adds another visit.

In NREL's data, the gap between a 7-day review and a 51-day submission-to-final timeline is the time spent on corrections, scheduling, installation and inspection. Of those, only corrections happen before the permit is issued.

Permission to operate: the utility's part

The building department's final inspection does not turn the system on. The utility does.

Eversource describes its interconnection application review as typically taking one to three weeks, and longer if it needs more details from the contractor. After the local inspection, the utility installs a new meter and then issues permission to operate.

Since the interconnection application can run in parallel with the building permit, file it early. The utility's review and the city's review do not need to happen one after the other.

Can you start installing before the permit is approved?

No. Building codes generally require the permit before the work. Massachusetts, for example, says work may not proceed without first filing an application with the building official and obtaining the required permit (780 CMR 105.1). An early start does not save time either, because the inspection, and the utility's meter and PTO after it, still wait on the issued permit.

How TaskHatch helps

We file residential solar permits and answer the reviewer's comments until the permit is issued. Standard filings go in within three business days, Priority within two and Express within one. Across our filings, the median time to issuance through full plan review is 8 business days, and same day where the city uses SolarAPP+. Filing starts at $150 per project with plan check comments included; if the jurisdiction needs new documents from you, the resubmittal is $75. Inspection coordination through final is $100 per project.

Sources

Send us the project.

You shouldn't have to become an expert in every city's permit process just to keep crews working.

$150 to file. $100 to run your inspections through final. City comments never billed, however many rounds.

Questions? Email us at permits@getpromatic.com

Start a Project

No setup. No contract. No minimum.