Why do solar inspections fail? What inspectors check
Solar inspections usually fail because the install does not match the approved plans, labels are missing, or the inspector cannot safely reach the work.
A solar permit can sail through plan review on the first pass and still fail in the driveway. The reviewer approved a drawing. The inspector is looking at a roof, a ladder, and whatever the crew actually installed, which is not always the same thing.
Why do solar inspections fail?
Most solar inspections fail for one of three reasons: what was installed does not match the approved plans, a required label or marking is missing, or the inspector cannot safely get to the work and see it. After that come the technical items inspectors check on every job: grounding and bonding, wiring methods, the point of interconnection, and rapid shutdown.
Plan check rejections are a different problem, covered in the six reasons permits get kicked back. This post is about the field visit: what inspectors look at, and the questions installers usually have next.
What does a solar inspector check?
Jurisdictions publish their own checklists, and they read remarkably alike. Dearborn, Michigan's rooftop solar checklist has 19 items, and nearly every one is phrased as "matches the approved plan": module model and quantity, mounting and attachments, conduit, conductor sizes, overcurrent devices, disconnects, labels, and grounding connections. It also asks the inspector to confirm the rapid shutdown system is installed and working under NEC 690.12, and that working space is provided at inverters, disconnects and panels.
New Brighton, Minnesota's checklist walks through the NEC article by article: equipment listed for PV use, conductor sizing, overcurrent protection, wiring methods, grounding, and the interconnection rules in Article 705.
Where SolarAPP+ issued the permit, the inspector works from the SolarAPP+ inspection checklist instead of a plan set. It covers the interconnection method, main panel equipment, the inverter, installation details, roof and fire safety requirements, and signs and placards, with a pass box for each item.
The install does not match the approved plans
This is the failure that has nothing to do with workmanship. The crew did good work. It just was not the work on the plans.
Common versions:
- A different module or inverter than the one on the approved set, because the distributor was out
- More or fewer modules, or the array moved to a different roof plane
- Conduit routed a different way than the plan shows
- A breaker size or disconnect that changed during the install
Jurisdictions are direct about this. Rancho Cucamonga, California, says the installation shall match the plans at the time of inspection, and asks for revised plans to be submitted before calling for the inspection. Las Vegas says that if the design changes after the permit is issued, you are required to apply for a revision, and the revised plans have to be on site for the inspection.
SolarAPP+ is no shortcut here. Its help center notes that inspectors do not verify against a plan set, and that if an installer deviates from the approved design, anything outside the scope of eligibility would be discovered at inspection.
The fix: treat any equipment swap or layout change as a revision before the inspection, not a conversation during it. A revision filed on Tuesday costs less than a failed inspection on Thursday.
Labels and markings
Labels are the easiest item to get right and among the easiest to fail. The inspector can see them from the ground, and a missing one is a fail no matter how good the rest of the job is.
What checklists commonly look for:
- The permanent rapid shutdown label described in NEC 690.56(C), which Tempe, Arizona, calls out on its plan review checklist
- Labels at the PV disconnect and at the AC point of connection
- A placard or directory at each service disconnecting means showing every power source on the building (NEC 705.10)
- Labels on backfed breakers and disconnects
- The DC power source ratings at or next to the inverter or DC disconnect
Murrieta, California, puts it plainly: all required labels must be properly fixed in place. A label in the truck does not count.
The fix: build the label set from the label plan on the approved drawings, and have the crew photograph each one before they leave the site.
The inspector cannot reach or see the work
An inspector who cannot get on the roof, or cannot see inside the equipment, cannot pass it.
Several jurisdictions spell out what access means:
- A ladder that is set and secured. San Luis Obispo County asks for an OSHA-approved ladder, secured, extending at least three feet above the roof surface. Rancho Cucamonga wants it in place before the inspector arrives.
- Someone on site. Douglas County, Colorado, expects a contractor representative on site with the stamped, approved plans and permit package. Plymouth, Massachusetts, requires a representative at the final with all equipment open for inspection.
- Equipment open. Dearborn asks for all PV disconnects and breakers to be in the open position before the inspector verifies anything.
- Documents on hand. Murrieta asks for the approved plans, the inspection record card and the manufacturer's installation instructions.
Some inspectors also check the attic. Douglas County's checklist calls for a ladder at the attic access so the inspector can confirm the mounting hardware did not miss or damage the roof framing.
The fix: this is a scheduling and communication problem more than a technical one. Confirm who will be there, what they need to bring, and whether the homeowner needs to be home to open the house.
Grounding, bonding and wiring methods
These are the technical items that show up on every checklist. Inspectors look for:
- Racking, modules, inverters and other equipment grounded and bonded per the manufacturer's instructions
- A grounding electrode system that is in place and, where required, bonded between the DC and AC sides
- PV conductors over 30 volts in raceway, or guarded, where they are readily accessible
- Outdoor single conductors of the correct type, such as PV wire
- Exposed cables secured and supported so they will not be damaged
Some jurisdictions check grounding before the modules go on. Douglas County requires a rough electrical inspection for rail-mounted systems covering rail bonding, junction boxes, grounding hardware and the array ground. Plymouth requires a rough grounding inspection before any panels are installed. If the modules go on first, the inspector cannot see what they came to see. Our Plymouth permit page has the town's full solar inspection sequence.
The point of interconnection
Where the system ties into the house is where an approved design and the actual panel most often disagree. Dearborn checks that the inverter breaker sits at the opposite end of the busbar from the utility supply, unless the panel is center-fed or the combined breaker ratings fit within the bus rating. New Brighton checks that a supply-side disconnect is readily accessible and within 10 feet of the connection point.
Code section numbers here have moved between NEC editions, so check which edition your jurisdiction has adopted before you rely on a reference.
Rapid shutdown
NEC 690.12 requires rooftop PV on buildings to have a rapid shutdown function. On the plans, that is a device list and a switch location. In the field, some inspectors test it. Plymouth's final electrical inspection includes a rapid shutdown test, and Dearborn's checklist asks the inspector to confirm the system is installed and operational.
A rapid shutdown device that was installed but never commissioned, or an initiation switch that is not where the plans say, fails the same way a missing device does.
What happens after a failed solar inspection?
The inspector leaves a correction notice, the crew fixes the items, and the job goes back on the inspection calendar. Some jurisdictions charge for the return trip. Rancho Cucamonga warns that a reinspection fee may be assessed when the work is not ready.
The money is the smaller cost. Each failed inspection adds another wait for an open slot, and the utility usually waits for the final before it gives permission to operate.
A pre-inspection walk that catches most of this
Before you call for the inspection:
- Compare the installed modules, inverter, breakers and disconnects to the approved plan set, and file a revision for anything that changed.
- Walk the label plan and photograph every label in place.
- Confirm the ladder, the on-site contact, open equipment and attic access with the crew lead.
- Put the approved plans, permit card and installation manuals where the inspector can find them.
- Test rapid shutdown yourself.
How TaskHatch helps
We file residential solar permits and, with inspection coordination, schedule every inspection through final: we book the slot with the jurisdiction, confirm the homeowner, coordinate the license holder and check that the right documentation is on site. Inspection coordination is $100 per project. If an inspection fails, re-inspection is $50 to reschedule and re-coordinate the next visit.
Sources
- City of Dearborn, Michigan: Rooftop solar residential inspection checklist
- City of New Brighton, Minnesota: Solar photovoltaic inspection checklist
- SolarAPP+ Help Center: What's on the SolarAPP+ inspection checklist?
- SolarAPP+ Help Center: How does SolarAPP+ impact my inspection process?
- SolarAPP+ Help Center: How do I prepare for an inspection?
- City of Rancho Cucamonga, California: Standards for residential PV
- City of Tempe, Arizona: Residential photovoltaic plan review checklist
- City of Las Vegas: Residential photovoltaic solar permits
- City of Murrieta, California: PV system inspection checklist
- San Luis Obispo County, California: Photovoltaic inspection procedures
- Douglas County, Colorado: Photovoltaics inspection sequence checklist
- Town of Plymouth, Massachusetts: Solar electrical inspection requirements