Permits in Concord, MA
We file heat pump, solar, battery and generator permits with the Town of Concord's Building & Inspections Division, and book the inspections that Concord Light's heat pump rebates depend on.
Last checked November 2026 · From the town's and state's own pages · Send a correction
Concord building department
- Office that issues permits
- Town of Concord Building & Inspections Division
- Phone
- 978-318-3280
- Address
- 141 Keyes Road, 2nd Floor, Concord, MA 01742
- Office hours
- Monday to Thursday, 8 a.m. to 4 p.m.; Friday, 8 a.m. to noon
- How filings are submitted
- PermitEyes · An account is required. Electrical, gas, plumbing and sheet metal permits are filed online; allow at least 48 hours for review.
Heat pumps and HVAC
- The project electrician applies for a town electrical permit before work begins. That holds on a homeowner's own install too.
- Ductwork beyond minor repairs needs its own sheet metal permit and inspection. The town's form lists HVAC among the work types, and only licensed Journeyperson and Master Sheet Metal Workers can be issued one.
- Ground-source heat pumps need a Board of Health drilling permit before drilling starts.
- Concord Light doesn't pay a heat pump rebate until town records show the electrical inspection, and any required sheet metal inspection, approved. Its 90-day rebate application window starts on the later of those approval dates.
Scheduling inspections
The electrician calls the Electrical Inspector at 978-318-3235 between 8 and 9 a.m. on weekdays, and the town says those inspections can usually be completed within 5 to 7 days. Sheet metal inspections are booked through the Building Department at 978-318-3280, and plumbing and gas inspections with the Plumbing/Gas Inspector at 978-318-3276.
Rebate deadline tied to inspections
Concord Light's 90-day heat pump rebate window starts on the later of the electrical or sheet metal inspection approval date, and Concord Light checks those dates in the town's records. Applications that arrive after 90 days aren't eligible.
Where filings stall
- A rebate application that arrives after Concord Light's 90-day window. The clock starts at the last inspection approval, not at installation.
- Homes whose main heat is or was natural gas aren't eligible for Concord Light's heat pump rebate, and it can't be combined with a Mass Save rebate for the same equipment.
- Only the electrician can request the electrical inspection; the homeowner can't.
Massachusetts rules that apply
- Building work on one- and two-family homes has to be supervised by a Construction Supervisor License (CSL) holder or a registered design professional, and most work on existing owner-occupied homes also needs a Home Improvement Contractor (HIC) registration. Massachusetts does not recognize out-of-state contractor licenses.
- The state's one- and two-family building permit application asks for the CSL number, the HIC registration number and a workers' compensation affidavit. A permit is not issued without the affidavit.
- State guidance says installing a mini-split on a one- or two-family home triggers a building permit. A CSL is not needed for a basic install, but it is if building elements are cut or notched.
- Sheet metal work needs a licensed sheet metal worker and a permit from the local building department before work starts.
- Concord: Building & Inspections
- Concord: Building permit information
- Concord: Applications
- Concord: Sheet metal permit application
- Concord: Heat pump permit FAQ
- Concord: Inspection FAQ
- Concord Light: Heat pump rebates for your home
- Mass.gov: 271 CMR 9.00, sheet metal permits and inspections
- Mass.gov: When a Construction Supervisor License is required
- Mass.gov: Building permit application, one- or two-family dwelling
- Mass.gov: Mini-split permitting and licensing guidance
- Mass.gov: Sheet metal regulatory reminders