Permits in Framingham, MA
We file solar, battery, heat pump and generator permits with Framingham's Inspectional Services Division, which takes building, electrical, gas, mechanical, plumbing and sheet metal permits through OpenGov and publishes its own solar permitting checklist.
Last checked October 2026 · From the city's and state's own pages · Send a correction
Framingham building department
- Office that issues permits
- City of Framingham Inspectional Services Division
- Phone
- 508-532-5500
- Address
- 150 Concord Street, Room 203, Framingham, MA 01702
- Office hours
- Monday, Wednesday and Thursday 8:30 a.m. to 5 p.m.; Tuesday 8:30 a.m. to 7 p.m.; Friday 8:30 a.m. to 12:30 p.m.
- How filings are submitted
- OpenGov Permitting and Licensing · In use since July 1, 2025. An account is required.
Solar
- Every solar PV project in Framingham needs a building permit. Roof-mounted systems are filed as an "Alteration" and ground-mounted systems as "Other."
- Roof-mounted systems need a signed structural review from a Massachusetts engineer showing the roof can carry the system and the required snow loads.
- The electrical permit needs a one-line or three-line diagram and spec sheets for the panels, racking and inverter, and the work is done by Massachusetts-licensed electricians.
- Systems that don't meet zoning setbacks or height limits need a variance or special permit.
- Roof-mounted systems typically get two electrical inspections and one or two building inspections; ground-mounted systems get two of each.
Heat pumps and HVAC
- The portal has separate Mechanical Permit and Sheet Metal Permit applications.
- The Sheet Metal Permit lists HVAC as a work type, asks whether the applicant holds an unrestricted (J-1/M-1) or restricted (J-2/M-2) license, and asks for proof of liability insurance.
- A duct inspection is required before insulation is installed.
Standby generators
- The gas fitter permit and the electrical permit are separate applications on the portal.
- Same-day plumbing and gas inspection requests have to be made by 9:30 a.m.
Scheduling inspections
Inspections are booked by calling the Inspectional Services Division at 508-532-5500 on weekdays between 8:30 and 9:30 a.m. or between 4 and 5 p.m.
Where filings stall
- Exterior work visible from a public way in one of Framingham's six local historic districts needs a Certificate of Appropriateness from the Historic District Commission, whether or not a building permit is required.
- Projects near wetlands may need a Conservation Commission permit before the building application is processed.
- The residential application asks for CSL and HIC details, a workers' comp affidavit with the policy declaration page, and a debris removal affidavit, and says missing items lead to denial.
Massachusetts rules that apply
- Building work on one- and two-family homes has to be supervised by a Construction Supervisor License (CSL) holder or a registered design professional, and most work on existing owner-occupied homes also needs a Home Improvement Contractor (HIC) registration. Massachusetts does not recognize out-of-state contractor licenses.
- The state's one- and two-family building permit application asks for the CSL number, the HIC registration number and a workers' compensation affidavit. A permit is not issued without the affidavit.
- State guidance says installing a mini-split on a one- or two-family home triggers a building permit. A CSL is not needed for a basic install, but it is if building elements are cut or notched.
- Sheet metal work needs a licensed sheet metal worker and a permit from the local building department before work starts.
- Framingham: Inspectional Services
- Framingham: Applications
- Framingham: Solar permitting checklist
- Framingham: Residential building permit application
- Framingham: Sheet metal permit application
- Framingham: Plumbing and gas permit fees
- Framingham: Historic District Commission
- Mass.gov: When a Construction Supervisor License is required
- Mass.gov: Building permit application, one- or two-family dwelling
- Mass.gov: Mini-split permitting and licensing guidance
- Mass.gov: Sheet metal regulatory reminders